BBI completed a full roof replacement and exterior revitalization of the Alachua County Library District Headquarters while the facility remained fully occupied and operational throughout construction.
The project required careful sequencing, weather protection, and building envelope coordination to modernize aging exterior systems, address ongoing water intrusion issues, and protect active interior public spaces during construction.
THE CHALLENGE
Modernizing an aging public facility while protecting active operations and interior spaces.
The Alachua County Library District Headquarters required significant exterior modernization to address aging roofing systems, ongoing water intrusion concerns, and long-term building envelope performance issues.
The project involved complete removal of the existing clay tile roof system, replacement of all skylights, exterior repainting, storefront replacement at the upper cupola, and targeted landscape improvements across the active public facility.
Because the library remained fully operational throughout construction, BBI had to carefully coordinate work around active public access, occupied interior spaces, weather exposure risks, and ongoing daily library operations.
The project also required specialized coordination to address water intrusion issues while preserving existing stained-glass features integrated into the facility’s architecture.
THE BBI APPROACH
Building envelope modernization planned around uninterrupted public use.
BBI developed a phased execution strategy focused on maintaining continuous library operations while protecting the building and occupants throughout exterior construction activities.
Careful sequencing, temporary weather protection systems, and proactive coordination allowed roofing, storefront, skylight, and exterior restoration work to progress safely without disrupting daily public use of the facility.
BBI coordinated:
- Full roof replacement activities
- Skylight replacement sequencing
- Weather protection planning
- Active public access management
- Occupied space protection
- Exterior repainting coordination
- Storefront replacement and façade restoration
- Preservation of stained-glass elements
- Site logistics and material access
To resolve ongoing water intrusion at the upper cupola, BBI installed new storefront systems designed to restore the integrity of the building envelope while preserving important architectural features.
The completed modernization improved long-term durability, weather protection, energy performance, and exterior appearance while supporting uninterrupted public operations throughout the project.
PROJECT OUTCOMES
A fully modernized exterior delivered without interrupting public service.
BBI successfully completed the roof replacement and exterior revitalization while maintaining continuous library operations throughout construction.
Through disciplined planning, sequencing, and occupant protection measures, the project improved long-term building performance, restored the facility envelope, addressed ongoing water intrusion concerns, and preserved the functionality of an important public community resource.